The Water Service Design Group designed two new Waste Water Treatment Works for the area receiving a CEEQUAL excellent rating for their work.

Overview

Greyabbey and Kircubbin are located towards the northern end of Strangford Lough, Northern Ireland. In 2001 Water Service Design Group undertook the task of designing two new Waste Water Treatment Works for the area: one on the existing site at Greyabbey and the other at a new site at Monaghan Bank, Kircubbin.

About

Northern Ireland Water Service provides 575 million litres of clean water a day for almost 1.8 million people as well as treating 340 million litres of wastewater every day, and has approximately 1,300 staff

Background

The design included the most up to date process technology – Membrane Biological Reactors. Construction started on the Kircubbin site in April 2002 and at Greyabbey in June 2002. The contract was awarded to Geda Construction Ltd and EPS (Ireland) Ltd in consortium. Both sites were commissioned in August 2003.

Challenges

As Strangford Lough is an Area of Outstanding Natural Beauty, Area of Special Scientific Interest, and has a high environmental, cultural and heritage value with various bird and nature reserves, Water Service considered the potential effects of the construction on the appearance of the area as a whole, the effects on the ecologically sensitive surroundings and the effect on the local community. All of this had to be achieved within a tight budget.

Solutions

With the challenges in mind, the project constructed two ‘state of the art’ Wastewater Treatment works, housed in buildings which reflect the surrounding area in the choice of material, finished in basalt style cladding and slate effect roof, landscaped with indigenous plants and shrubs where the land had been previously agricultural fields or concreted areas. The local community was also considered with a high PR effort. Over the last 3-4 years Water Service representatives have given presentations and held discussions with council members, community representatives and members of numerous local nature and wildlife organisations. The project has taken on board feedback from these sessions and has tried to incorporate ideas, where possible, into the scheme. The contract used the NEC conditions of contract and was completed on time and to budget.

Benefits

It was due to the high attention of detail to the environmental, cultural and heritage, community relations and land use issues that achieved the CEEQUAL (now known as BREEAM Infrastructure) award. The project obtained a very high score of 91.9% – well into the Excellent Category.

Summary Greyabbey And Kircubbin Wastewater Treatment Works

Summary

Client:
Northern Ireland Water Service
Designer:
Northern Ireland Water Service
Construction:
Geda and EPS Consortium
Assessors:
Neil Brady
Version:
2, June 2003 | London, England, UK
CEEQUAL rating:
Excellent (91.9%) - Whole Team Award