Bridge replacement projects in Sweden gets CEEQUAL 'Very Good' rating

Bridge replacement projects in Sweden gets CEEQUAL 'Very Good' rating

The Swedish Transport Administration replaced two bridges on a highway where 70,000 vehicles cross every day. The project got a CEEQUAL rating of Very Good.

Overview

The Swedish Transport Administration needed to replace two bridges on the E4 highway, at one of Sweden’s busiest junctions – Rotebro – as the technical lifespan of the bridges had been reached. Rotebro is in the municipality of Sollentuna, halfway between Stockholm and Arlanda airport. Approximately 70,000 vehicles cross the bridges daily. For the work carried out the project received a CEEQUAL (now known as BREEAM Infrastructure) rating of Very Good.

About

The Swedish Transport Administration is a government agency in Sweden, controlled by the Riksdag and the Government of Sweden. It is responsible for long-term infrastructure planning for transport: road, rail, shipping and aviation.

Background

Under the bridges, there are municipal streets with approximately 25,000 vehicles. Here the railway “Ostkustbanan” also crosses with around 600 trains per day where the fastest trains to Arlanda airport have been able to pass at a speed of 200 km/h through the construction site. The train traffic is active all day on every day of the year, meaning that this is a complicated project, in a very busy traffic setting.

Challenges

Safety and accessibility are the most prioritised goals of the project. Because of this, a key focus of the project was the identification of risks and the management over the course of the project. This increases the possibility to proactively prevent risks. Over 300 million journeys have passed through the site without being affected, and the accessibility has been one of the main challenges of the construction. The challenge in safety and accessibility has not only focused on train and car traffic, but also on cyclists and pedestrians. Since the construction site has been adjacent to a commuter train station it has been important to always keep pedestrians informed about how to get to the station. Another challenge was to demolish the old bridges without affecting the train traffic under the bridges.

Solutions

The unique aspect of this project is that new technology which makes it possible to perform most of the work without influencing the existing traffic. A permanent bridge was built in a temporary position which is then pushed into place. This new technique reduced the disturbance to traffic as well as time and costs.

A calculation of carbon dioxide emission savings, using the chosen technique has been made, and has been calculated at 122 tons of CO2. That corresponds to 91,000 km of car driving, or 60 flights between Stockholm and London. This reduction is due only two bridges being necessary in the solution from NCC instead of five bridges in the original proposal. The calculation does not include the absence of emissions from lines of cars, which would have been the case in the original proposal.

Benefits

There were many benefits that came out of the project:

Turn-key project

The project was procured as a turn-key contract. That means the Swedish Transport Administration leaves a greater responsibility to the contractor, who in addition to the realisation of the project also is responsible for material choices – giving NCC a greater freedom. For the Swedish Transport Administration it meant that more time could be spent on planning and on focusing on the function. NCC proposed a solution to the Swedish Transport Administration where the accessibility during the construction phase was very good at the same time as the price for the contract was around 25 percent lower than the original estimate from the Swedish Transport Administration.

Environmental award

The project has received a lot of attention. At the Concrete Gala in 2013 it won the environmental prize with the motivation that the rebuilding of the Rotebro bridges is Sweden’s first environmentally certified infrastructure project. In 2016, the bridges were one of the second place prizewinners in the Construction of the Year. The Swedish Transport Administration’s new procurement strategy, was opened up for new thinking by the contractor NCC and enabled a cheaper, more efficient and environmentally friendly solution when rebuilding the bridges. NCC built a permanent bridge in a temporary position, and then pushed it into place laterally. The judgement was that it was a brilliantly smart solution, both cheaper and less disturbing for traffic.

Other

The Highway E4 Rotebro project was chosen as a pilot for certification through CEEQUAL. The work has been done in cooperation with the contractor NCC. The project was the first Whole Team Award with Interim to be performed in Sweden, and included the planning, design and construction phase. Our British verifier Catherine Arotsky has been a very pleasant acquaintance who quickly got into Swedish conditions and was very keen and helpful.

Summary Swedish Transport Administration

Summary

Client:
Swedish Transport Administration
Designer:
Centerlöf & Holmberg / ÅF
Construction:
NCC Construction Sweden AB
Assessors:
Kristine Ek, Ragnhild Karlsson
Version:
4, March 2016 | Rotebro, Sweden
CEEQUAL rating:
Very Good – Whole Project Award + Interim
Asset Publisher
Asset Publisher